Installing the IAC
3-32
EATON Powerware
®
9390 IAC-B and IAC-T Installation and Operation Manual S 164201590 Rev C powerware.com
Installation Checklist
- All packing materials and restraints have been removed from each cabinet.
- Each cabinet in the UPS system is placed in its installed location.
- Shipping brackets are installed on the cabinet and bolted to the floor for permanent installations.
- All conduits and cables are properly routed to the IAC.
- All power cables are properly sized and terminated.
- IAC auxiliary contact signal wiring is connected from the IAC to the UPS.
- A ground conductor is properly installed.
- Air conditioning equipment is installed and operating correctly.
- The area around the installed UPS system is clean and dust-free. (The UPS and IAC must be installed on a
level floor suitable for computerorelectronicequipment.)
- Adequate workspace exists around the IAC and other cabinets.
- Adequate lighting is provided around all UPS system equipment.
- A 120 Vac service outlet is located within 25 feet of the UPS and IAC equipment.
- The debris shield covering the IAC cabinet ventilation grill is removed.
- Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.