INSTALLING THE UPS SYSTEM
EATON Powerware
®
9315 UPS (500–750 kVA) Installation and Operation Manual S 164201691 Rev 2 www.powerware.com
3-6
3.5 Installing Input/Rectifier Customer Connections
NOTE If you are installing connections to the Battery I/O terminal connections and terminal board CB2TB,
install conduit between each device and the UPS cabinet for wiring these options.
See paragraph A.5 on page A-28 for the interface point locations within the UPS
cabinet.
To prepare the UPS for wiring to customer connections:
1. Verify that the UPS system is turned off and all power sources are removed. See
“Shutting Down the UPS and Critical Load” on page 9-6 for shutdown
instructions.
2. Remove the sheet-metal shield covering the input terminal area in the
Input/Rectifier cabinet to gain access to the Battery I/O customer interface
and CB2TB. See Figure A‐12 on page A-22 for the shield location.
3. See paragraph A.5 on page A-28 for terminal assignments, and wiring and
termination requirements.
3.6 Installing Output/Inverter Customer Connections
NOTE If you are installing connections to a REPO device, building alarm, or relay contacts, install conduit
between each device and the UPS cabinet.
See paragraph A.5 on page A-28 for the interface point locations within the UPS
cabinet.
To prepare the UPS for wiring to customer connections:
1. Verify that the UPS system is turned off and all power sources are removed. See
“Shutting Down the UPS and Critical Load” on page 9-6 for shutdown
instructions.
2. See paragraph A.5 on page A-28 for terminal assignments, and wiring and
termination requirements.
3.7 Installing Accessories
To install an optional REPO switch, see Chapter 5, “Installing a Remote Emergency
Power-off Control.” To install optional accessories [such as the Remote Monitor
Panel (RMP) or X-Slot connections], see Chapter 6, “Installing Optional
Accessories.” When accessory installation is complete, proceed to paragraph 3.8.
3.8 Initial Startup
Startup and operational checks must be performed by an authorized Eaton Customer
Service Engineer, or the warranty terms specified on page 15-1 become void. This
service is offered as part of the sales contract for the UPS. Contact your Eaton service
representative in advance (usually a two week notice is required) to reserve a